Construction Log Report
Printed:
2/26/2007
 3:48:42AM
Report Created by KitLog Pro
T-19
Team Tango
Tango
Kit Manufacturer:
Kit Model:
Kit Serial Number:
,  
Andy Gamache
Owner City/State/Zip:
Owner Address:
Owner Name:
Hours 
Category
Date
Partner
Manual Reference #
9/26/2003
Airframe Kit
Peter Chapin
 2.50
When I came in Peter gave me the nickel tour then set me to work sanding the fuselage seam using an angle grinder with a 
36 grit wheel.  After sanding we laminated two layers of glass 3widethen went to lunch while it cured.    After lunch the 
seam was cured so we sanded down the high spots using the same angle grinder with the same 36 grit wheel.  With few 
exceptions  The angle grinder will ALWAYS have 36 grit on it.
Raw fuselage seam
Fuselage seam after glassing
Peter Chapin helping sand the high 
spots on the glassed seam.
9/26/2003
Airframe Kit
Peter Chapin
 0.50
Bolted the front of the fuselage to the front jig support.  The tail was bolted to a saddle jigThe saddle jig was then positioned 
with wedges.  After getting the fuselage perfectly level on the pitch and roll axisall wedges and supports were bonded into 
place to ensure the fuselage stayed that way.
Firewall is bolted to hold it level
The tail is bolted to hold it level
9/26/2003
Airframe Kit
Peter Chapin
 0.50
Marked the location of the wings using a sharpie and a pattern cutout.  The leading edge was measured back from the 
firewall.    Sanded off all the gel coat in the area of the wings and one inch around it.
Page 1 of 114